OVERVIEW

GPTL was incorporated on October 26, 2015. GPTL entered into a TSA on March 4, 2016. The GPTL project was awarded by the Ministry of Power on March 17, 2016 for a 35-year period from the scheduled commercial operation date of the GPTL project, on a BOOM basis. We acquired 49% of GPTL (with 100% economic interest) from SGL4 in August, 2020.

Details of GPTL’s transmission lines, substations and line bays are set forth as follows:

TRANSMISSION LINE / SUBSTATION ROUTE LENGTH (CKMS) SPECIFICATIONS COMMISSION DATE EXPIRY TERM OF TSA
Aligarh - Prithala 99 400 kV D/C HTLS line August 06, 2019 July 2054
Prithala – Kadarpur 55 400 kV D/C HTLS line December 7, 2019 July 2054
Kadarpur-Sohna Road 22 400 kV D/C HTLS line March 21, 2020 July 2054
LILO of Gurgaon Manesar 2 400 kV D/C Quad line March 13, 2020 July 2054
Neemrana – Dhonanda 93 400 kV D/C HTLS line February 25, 2019 July 2054
Kadarpur substation - 400/220 kV, 2 x 500 MVA December 11, 2019 July 2054
Sohna Road substation - 400/220 kV, 2 x 500 MVA April 13, 2020 July 2054
Prithala substation - 400/220 kV, 2 x 500 MVA August 8, 2019(1) July 2054
Dhonanda substation - Two 400 kV line bays February 25, 2019 July 2054

(1) Deemed commission date.