OVERVIEW

NTL was incorporated on July 29, 2013. NTL entered into a TSA on January 2, 2014. The NTL project was awarded by the Ministry of Power on May 23, 2014 for a 35-year period from the scheduled commercial operation date of the NTL project, on a BOOM basis. We acquired NTL from the Sterlite Sponsor in June, 2019.

NTL In The GridThe NTL project was expected to deliver over 2,000 MW of electricity from Punjab to the Kashmir Valley by strengthening the transmission system in the states of Jammu and Kashmir and Punjab. The Jalandhar-Samba 400 kV D/C transmission line was commissioned in June 2016 and the Uri-Wagoora transmission line was commissioned on September 2, 2018.

Details of NTL’s transmission lines and substations are set forth as follows:

TRANSMISSION LINE / SUBSTATION ROUTE LENGTH (CKMS) SPECIFICATIONS COMMISSION DATE EXPIRY TERM OF TSA
Jalandhar—Samba 270 400 kV D/C June 24, 2016 June 2051
Samba—Amargarh 547 400 kV D/C September 2, 2018 September 2053
Uri—Wagoora 14 - September 2, 2018 September 2053
Amargarh Substation - 400/220 kV D/C GIS Substation with 735 MVA of transformation capacity September 2, 2018 September 2053