OVERVIEW

OGPTL was incorporated on April 17, 2015. OGPTL entered into a TSA on November 20, 2015. The OGPTL project was awarded by the Ministry of Power on January 6, 2016 for a 35-year period from the scheduled commercial operation date of the OGPTL project, on a BOOM basis. We acquired OGPTL from the Sterlite Sponsor in July, 2019. The Jharsuguda-OPGC 400kV D/C transmission line was commissioned in August 2017 and Raipur- Jharsuguda line was commissioned in April, 2019.

Details of OGPTL’s transmission lines are set forth as follows:

TRANSMISSION LINE / SUBSTATION ROUTE LENGTH (CKMS) SPECIFICATIONS COMMISSION DATE EXPIRY TERM OF TSA
Raipur – Jharsuguda 608 765kV D/C April 6, 2019 April 2054
Jharsuguda – OPGC 103 400 kV D/C August 30, 2017 July 2052