OVERVIEW
Solar Edge is engaged in the business of setting up, generating, and selling of renewable power from its ground mounted solar power plants located at Beed 104.00 MWp (80.00 MW AC) & Jalgaon 65.00 MWp (50 MW AC) in Maharashtra. Solar Edge had entered PPA with SECI for implementation of 169.00 MWp (130.00 MW AC) solar photovoltaic power generation unit in the state of Maharashtra, to sell electricity for a period of 25 years from COD.
Details of Solar Edge’s project elements are set forth as follows:
Element | Location | Specifications | Actual commission date | Expiry of term of the PPA |
---|---|---|---|---|
Beed | Maharashtra | AC capacity: 80 MW; DC capacity: 104 MWp | April 2018 | 25 years from declared COD date |
Jalgaon | Maharashtra | AC capacity: 50 MW; DC capacity: 65 MWp | April 2018 | 25 years from declared COD date |