OGPTL was incorporated on April 17, 2015. OGPTL entered into a TSA on November 20, 2015. The OGPTL project was awarded by the Ministry of Power on January 6, 2016 for a 35-year period from the scheduled commercial operation date of the OGPTL project, on a BOOM basis. We acquired OGPTL from the Sterlite Sponsor in July, 2019. The Jharsuguda-OPGC 400kV D/C transmission line was commissioned in August 2017 and Raipur- Jharsuguda line was commissioned in April, 2019.

Details of OGPTL’s transmission lines are set forth as follows:

Transmission line/ Substation Route Length (ckms) Specifications Commission Date Expiry of TSA Term Contribution to Total Tariff
Raipur – Jharsuguda 608765kV D/C April 6, 2019April 205494%
Jharsuguda – OPGC 103400 kV D/CAugust 30, 2017July 20526%

The average quarterly availability of OGPTL since commissioning is set forth in the table below: